13 Central Heating

Sunday 10 November 2013 / 1224

New hall radiator to replace one which burst, fitted and plumbed in.

Floor

Wednesday 7th November 2012 / 21:55

An evening session. Working across putting noggins in and getting the levels right.

12 Bathroom

Friday 23rd May 2014 / 08:56

The walls are filled with acoustic insulation.

13a Bathroom 3

Monday 29th December 2014 / 12:53

Shower door in position to check it will be ok. It will not be properly fitted until after tiling and grouting.

13 Bathroom 3

Monday 29th December 2014 / 12:53

Shower door in position to check it will be ok. It will not be properly fitted until after tiling and grouting.

Roof 4

Friday 24th February 2012 / 10:20

All of the old roof timbers and felt that are not needed have been removed now.

Stud Walls

Friday 1st February 2013 / 14:15

Removing part of existing door frame to allow for stud wall.

14 Central Heating

Sunday 10th November 2013 / 13:22

Drilling 125 mm dia hole for flue with diamond core drill borrowed from William. The hole slopes back to the boiler at 3 degrees to allow condensate to drain back into the boiler.

Floor

Wednesday 7th November 2012 / 21:56

Moving the bath to yet another position. This should mean the floor can be built within one metre of the wall.

13 Bathroom

Friday 23rd May 2014 / 14:23

More acoustic insulation and foam tape on all studs. Cables through studs are shielded with steel plates.

14 Bathroom 3

Tuesday 30th December 2014 / 19:13

The first tile.

Stud Walls

Friday 1st February 2013 / 16:06

The first piece of plaster board goes up.

15 Central heating

Sunday 24th November 2013 / 18:30

Chris came round and helped put the boiler up on the wall.

Floor

Saturday 10th November 2012 / 15:06

14 Bathroom

Sunday 25th May 2014 / 15:30

More wadding and plumbing brought through Versapanel ready for sink.

15 Bathroom 3

Wednesday 31st December 2014 / 11:56

New year’s eve and things are progressing. The mosaic tiles on the internal curve are a pain, they slither around and the adhesive comes through the gaps.

Walls – gable end

Sunday 26th February 2012 / 15:20

Gable end inner block work done. Wall ties are arranged to allow space for cavity trays when fitted.

Stud Walls

Friday 1st February 2013 / 18:19

Relatively rapid progress.

16 Central Heating

Monday 9th December 2013 / 14:44

Graham the plumber has been here since 8:45 this morning commissioning the boiler. Everything’s gone fine, the boiler’s running and tests are being done so that it can be ‘benchmarked’. Tests occurring in this picture are: flue gasses sampled, radiator circuit output temperature measured, gas pressure measured whilst boiler runs at full power.