65 Conservatory

Saturday 23rd June 2018 / 09:40
As it’s hot we’ve put hessian on top of the concrete to slow down the drying/curing. I’m spraying it with water every few hours.

66 Conservatory


Friday 6th July 2018 / 16:47
Starting on the electrics first fit.

67 Conservatory


Saturday 14th July 2018 / 14:32
I’m putting three lighting circuits in. Floor, sides and top.

68 Conservatory


Monday 16th July 2018 / 20:25
Plaster boarding using dab and dot. Not too difficult really.

69 Conservatory


Friday 20th July 2018 / 17:19
More plaster boarding.

70 Conservatory


Saturday 28th July 2018 / 14:01
Today I’m getting this lock in the right place. It’s tricky on these overlapping doors because the lock has to come out beyond the body of the door, flush with the flange, or whatever it’s called in door terminology.

71 Conservatory


Sunday 19th August 2018 / 11:37
Fitting the windowsills.

72 Conservatory


Monday 27th August 2018 / 12:48
It’s bank holiday Monday and I’ve started tiling the floor.