50 Conservatory

Wednesday 9th May 2018 / 12:01

Floor insulation delivered.

51 Conservatory

Saturday 26th May 2018 / 13:27

Got the Gutter up and linked into the square down pipe.

52 Conservatory

Monday 28th May 2018 / 12:19

Bank holiday today and I’m starting to get the cables in before putting the insulation down.

53 Conservatory

Monday 28th May 2018 / 13:44

Putting the damp proof membrane down.

54 Conservatory

Monday 28th May 2018 / 18:09

All the insulation’s down now, including the bit round the edge to stop heat from the slab leaking into the walls.

55 Conservatory

Sunday 3rd June 2018 / 10:41

This is the underfloor heating kit.

56 Conservatory

Sunday 3rd June 2018 / 11:32

Insulation joints taped.

57 Conservatory

Sunday 3rd June 2018 / 13:40

Vapour barrier is down and I’ve just started laying out the underfloor heating pipe.

58 Conservatory

Sunday 3rd June 2018 / 16:46

Just over half the pipes done. There are two circuits.

59 Conservatory

Sunday 3rd June 2018 / 17:44

All done. Ready to go on holiday to Cornwall tomorrow.

 

60 Conservatory

Friday 15th June 2018 / 14:16

Pressurising the under floor heating circuits to 10 bar to check for leaks.

61 Conservatory

Friday 22nd June 2018 / 09:28

Today we are screening the floor. Nick and I are shovelling, barrowing and general help and Neil and William are doing the clever bit. The screed is pre-mixed. It’s a fairly dry mix.

62 Conservatory

Friday 22nd June 2018 / 10:06

William and Neil doing the difficult bit. Bits of wood are arranged to get the height right, then taken out and back filled.

63 Conservatory

Friday 22nd June 2018 / 12:18

Nick and I took William’s truck up to Nursling to pick up some more screed.

64 Conservatory

Friday 22nd June 2018 / 12:48

Getting towards the end. Hessian laid over the top and sprayed with water to slow down ‘going off’ as the weather it hot.