1 3rd room

Saturday 5th November 2016 | 11:30

Removing the old floor boards.

2 3rd bedroom

Sunday 6th November 2016 | 09:37

More floor removal.

3 3rd bedroom

Friday 11th November 2016 | 18:56

I’ve decided to replace all the joists as well as the floor boards, so it’s turned in to a much bigger job.

4 3rd bedroom

25th November 2016 | 11:11

I’m going to lay concrete with a DPM under the floor to keep the damp out, so I’m having a few tonnes of materials delivered to be made into concrete by Nick.

5 3rd bedroom

Fri 9th December 2016 / 12:45

Concrete is down now and I’m wrapping the edges of the DPM over the riser walls.

6 3rd bedroom

Friday 9 December 2016 / 12:45

Concrete has set.

7 3rd bedroom

Friday 9th December 2016 / 15:06

Starting to put the insulation and joists in.

8 3rd bedroom

Saturday 10th December 2016 / 17:48

I’ve bought and plumbed in a new radiator to replace the old one. It was the only one I didn’t replace when I put the heating system in.

9 3rd bedroom

Sunday 11th December 2016 / 17:48

Insulation and joists in with vapour barrier ready to position.

11 3rd bedroom

Saturday 5th January 2017 | 15:42

I’ve made these skirting boards using a router to create the angle as I couldn’t buy any to match the existing ones.

13 3rd bedroom

Saturday 18 February 2017

All finished, decorated with carpet laid and some furniture in.