Posted on 3 3rd bedroom Friday 11th November 2016 | 18:56 I’ve decided to replace all the joists as well as the floor boards, so it’s turned in to a much bigger job.
Posted on 4 3rd bedroom 25th November 2016 | 11:11 I’m going to lay concrete with a DPM under the floor to keep the damp out, so I’m having a few tonnes of materials delivered to be made into concrete by Nick.
Posted on 5 3rd bedroom Fri 9th December 2016 / 12:45 Concrete is down now and I’m wrapping the edges of the DPM over the riser walls.
Posted on 7 3rd bedroom Friday 9th December 2016 / 15:06 Starting to put the insulation and joists in.
Posted on 8 3rd bedroom Saturday 10th December 2016 / 17:48 I’ve bought and plumbed in a new radiator to replace the old one. It was the only one I didn’t replace when I put the heating system in.
Posted on 9 3rd bedroom Sunday 11th December 2016 / 17:48 Insulation and joists in with vapour barrier ready to position.
Posted on 11 3rd bedroom Saturday 5th January 2017 | 15:42 I’ve made these skirting boards using a router to create the angle as I couldn’t buy any to match the existing ones.
Posted on 13 3rd bedroom Saturday 18 February 2017 All finished, decorated with carpet laid and some furniture in.