Saturday 17th December 2011

After a week of stormy weather, a clear blue sky. I’ve even got washing on the line today.

The first of the three steel beams (steel #1) is in position now. Brought in through the front door and manoevured out through a small hole in the tiles. William must have been pleased when this went in as he sent a picture to my phone when it was in position.

Steel 2

Thursday 9th February 2012 / 22:06

Padstone for steel #2 to right of fire place. Other end bolts to steel #1. A very non-invasive installation, I thought.

Steel 3

Friday 24th February 2012 / 10:10

Steel #2 bolts to a welded plate on the end of steel #1 with the far end resting on the padstone in the previous picture.