Walls 13

Friday 28th October 2011 / 0949

New inner skin joins to existing using plate bolted to wall.

Walls 14

Saturday 12th November 2011 / 1121

The weather’s been rainy which has made building the outer skin brick work difficult so they’ve rigged up some shelter. You can see that I’ve moved the corrugated roof panels up to allow better access.

Walls 15

Saturday 12th November 2011 / 11:21

The inner skin is up to plate level.

Walls 16

Saturday 19th November 2011 / 10:35

After a couple of relatively dry weeks and sporadic activity the outer skin up to plate level.

Walls 17

Saturday 19th November 2011 / 10:36

Outer skin up to plate level. New brickword starts just beyond down pipe.

Walls – gable end

Sunday 26th February 2012 / 15:20

Gable end inner block work done. Wall ties are arranged to allow space for cavity trays when fitted.